Scope of project:

To Develop 29.2 ha of irrigation under gravity.

Specifications of all Dams and furrows to be done by KVM Energy Projects.

Design, procurement and installation of 29.2 ha of irrigation to be done by KVM Energy projects.

Project equipment supplied:

  • 3 centre pivots totalling an area of 18 ha
  • 11.2 ha of permaset irrigation
  • All piping and fittings for the irrigation system