Scope of project:
To design, construct and install a pump house that can deliver 900 cubic meters of water per hour to a gravity dam situated 36m higher than holding dam. The electricity used is to be produced from solar modules.
Project equipment supplied:
- Design and construct a pump house that will be able to accommodate 3 x 55KW motors and pumps.
- Design and install 86.45KWp of solar modules.
- 3 x 27,6KW ABB Grid Tie Inverters
- Install one 55KW motor and pump.